Following a July 2026 inspection, EMB-Negros Island Region issued a notice of violation dated 10 August 2026 against the Bacolod City government over its sanitary landfill in Barangay Felisa, citing the Philippine Clean Water Act (RA 9275) for water discharged from the landfill and PD 1586 for operating Cells 4 and 5 without an Environmental Compliance Certificate. The city says Cell 4 has operated since August 2024, before the leachate pond was finished in December 2024, and that its ECC application remains pending at EMB. City Administrator Mark Steven Mayo questioned why the notice named only the LGU and not contractor IPM Construction and Development Corporation, which the city says was responsible for securing the ECC.
This case is documented in public reporting. Every fact on this page comes from the sources below, which are kept against the case so the record can be checked.
Bacolod City Government · Aug 25, 2026
Every change of state, timestamped, oldest first. Entries are added, never edited or removed, so the record of how long something took cannot be quietly improved later.
Notice of violation issued to Bacolod City for Clean Water Act breaches and operating Cells 4 and 5 without an ECC.
Recorded by EMB-Negros Island Region
City reiterated compliance with landfill requirements and asked EMB to clarify why the contractor was not also cited.